*UPDATED June 23* Information Bulletin: Government of Canada, OPG & CNSC appeal Darlington New Nuclear Plant court decision
The Attorney General of Canada, Minister of the Environment, Minister of Fisheries and Oceans, Minister of Transport, Canadian Nuclear Safety Commission (CNSC) and Ontario Power Generation (OPG) have notified us they will try to resurrect nuclear expansion project in Darlington, Ontario.
Federal Court nixes approval of new nuclear reactors
Press Release - Environmentalists are applauding a landmark Federal Court ruling that puts the brakes on building expensive and risky new nuclear reactors in Ontario.
Environmentalists in court to demand proper review of nuclear risks
Lawyers for environmental groups ask a Federal Court today to order the Canadian Nuclear Safety Commission (CNSC) to redo its environmental review of Ontario Power Generation’s (OPG) plan to rebuild and run the aging Darlington nuclear reactors for three more decades.
Waterkeeper submits concerns with Darlington Refurbishment Follow-Up Program
The Canadian Nuclear Safety Commission invited the public to comment on a draft follow-up program for the refurbishment of the Darlington Nuclear Power Plant. Here's what we said:
Lake Ontario Waterkeeper has concerns about the Project, the Follow-Up Program, and this review process. We are very concerned about the environmental impacts of the Project, and we are not at all satisfied that the Follow-Up Program will protect Lake Ontario.
Environmental groups launch Federal Court challenge to Darlington refurbishment
“It's our view that the regulator did not even consider commonly-used, affordable ways to avoid killing millions of fish. Considering that Lake Ontario is in decline and that fish populations are a fraction of what they should be, this is unacceptable. To make matters worse, failure to consider impacts on fish is just one of many ways that we believe this environmental assessment process failed to meet legal standards,” says Mark Mattson, President of Lake Ontario Waterkeeper.
Darlington nuclear refurbishment gets go-ahead
Lake Ontario Waterkeeper raised serious concerns about the impacts on fish from these nuclear power plants. Darlington nuclear power plant sucks up enough Lake Ontario water to drain an Olympic-sized swimming pool in just 15 seconds. It does this 24 hours a day, 7 days a week in order to keep the nuclear reactors cool. In the process, millions of fish, eggs, and larvae are crushed and killed. This outdated cooling water system kills more fish than any other technology on the market.